The Port Authority of the Balearic Islands (APB) has awarded a contract for adaptation work on the sea wall and paving of the fisherman's wharf at the Port of la Savina.

The sea wall of the fisherman's wharf was part of a Port of la Savina expansion project undertaken in December 1992. The project sought to rearrange ship traffic and to create a new mooring line for smaller vessels.

Over the years, the APB has, both directly and through company concessions, undertaken diverse adaptation projects of the wharf, such as the technical dock modifications for smaller fishing and leisure vessels at the Port of la Savina.

After several inspections conducted during this period, it has become clear that the sea wall is not in a good condition due to defects in its construction, which would not have been possible to detect were it not for the quality control and monitoring of the works.

Therefore, repair and adaptation work of the sea wall and the paving of the fisherman's wharf at the Port of la Savina is to start this autumn.

The works under this project have been awarded to Matías Arrom Bibiloni S.L., for €166,000.

In addition to this action, another tender process is underway for the adaptation and improvement works of the fishing quay, which has an initial budget of €538,779.30.